Chaince Digital Holdings subsidiary Chaince Compute entered a binding agreement on November 19, 2026, to form a 60/40 joint venture with Bitlakedata Inc. The project aims to develop an AI/HPC data center in Big Lake, Texas, starting with a 5 MW phase. The venture has a potential capacity of up to 25 MW, contingent on utility approvals, tenant acquisition, and the signing of definitive operating agreements within 90 days.
On November 19, 2026, Chaince Compute signed a binding Joint Venture Framework Agreement to develop an AI/HPC data center in Big Lake, Texas, taking 60% of a venture with a 5 MW first phase and potential to expand to up to 25 MW. This gives the company its first announced AI data center project, but the deal is heavily conditional: AEP Texas must confirm the parcel can be served, tenants must be secured, and either party can terminate if definitive documents are not signed within 90 days.
- ▲ Binding Joint Venture Framework Agreement signed November 19, 2026 for an AI/HPC data center in Big Lake, Texas
- ▲ Potential expansion to up to 25 MW of power capacity across three phases
- ▼ Phase 1's 5 MW is subject to written confirmation from AEP Texas that the separate parcel can be served
- ▼ Either party may terminate if the joint venture is not formed within 90 days