Vizsla Silver has pushed back its targeted first silver production at the Panuco project in Mexico from the second half of 2027 to the second half of 2028. The company cited permitting, site readiness, and construction timing as primary factors for the delay, following a challenging year that included a tragic incident in January 2026. While engineering is 50% complete and 85% of plant equipment is ordered, the firm has not updated its feasibility economics for potential cost escalation.
Vizsla Silver pushed its targeted first silver production at Panuco back a full year, from H2 2027 to H2 2028, citing permitting, site readiness and construction timing after the tragic events of January 2026. A one-year delay pushes out cash flow from a project with a 7-month payback and 111% IRR, and the company warns it has not updated the economics for cost escalation or financing costs. Offsetting positives are real progress on engineering (~50% complete), ~85% of process plant equipment ordered, and an unchanged feasibility baseline.
- ▼ First silver production target revised from H2 2027 to H2 2028
- ▼ US$5 million initial commitment to the Vizsla Foundation plus a share of future profits
- ▲ Feasibility economics (NPV US$1.8 billion, IRR 111%) not yet restated for the later schedule, so cost escalation and financing costs could erode value
- ▲ Return to site remains conditional on security assessment with Mexican federal authorities; further slippage possible